Contract Agreement Amount

Rs. 1,78,79,402

Physical Progress

100.00%

Financial Progress

94.88%

Remaining Payment

Rs. 5

Roadway excavation, Structural works and bituminous pavement works at Jhumsa- Baanstari section of Siddhartha highway.

Office: सडक डिभिजन, पाल्पा (27)

Fiscal Year: 077-78

100.00%

Contract Date: 29-Apr-21

Start Date: 29-Apr-21

Completion Date: 09-Jul-2021 (EOT Not Done)

Project Description

No description available.