Contract Agreement Amount
Rs. 55,55,981
Physical Progress
0.00%
Financial Progress
94.85%
Remaining Payment
Rs. 5
Black top work on approach road (left Bank) and pier protection work of Sunkoshi River Bridge, Katari - Okhaldhunga
Office: डिभिजन सडक कार्यालय, हर्कपुर, ओखलढुङगा (175)
Fiscal Year: 075-76
Contract Date: 6-Mar-19
Start Date: 13-Mar-19
Completion Date: 10-Jul-2019 (EOT Not Done)
Project Description
No description available.