Contract Agreement Amount

Rs. 1,79,21,104

Physical Progress

95.08%

Financial Progress

94.85%

Remaining Payment

Rs. 5

Upgrading and Improvement of Krisnanagar-2, Sirsehawa, Balanagar, Lalpur, Jhulaniya Chauraha Road, Kapilvastu

Office: सडक डिभिजन, कपिलवस्तु (29)

Fiscal Year: 078-79

95.08%

Contract Date: 13-Jan-22

Start Date: 13-Jan-22

Completion Date: 03-Jan-2023 (EOT Done)

Project Description

No description available.