Contract Agreement Amount
Rs. 1,79,21,104
Physical Progress
95.08%
Financial Progress
94.85%
Remaining Payment
Rs. 5
Upgrading and Improvement of Krisnanagar-2, Sirsehawa, Balanagar, Lalpur, Jhulaniya Chauraha Road, Kapilvastu
Office: सडक डिभिजन, कपिलवस्तु (29)
Fiscal Year: 078-79
Contract Date: 13-Jan-22
Start Date: 13-Jan-22
Completion Date: 03-Jan-2023 (EOT Done)
Project Description
No description available.