Contract Agreement Amount

Rs. 1,31,68,245

Physical Progress

100.00%

Financial Progress

94.77%

Remaining Payment

Rs. 5

Construction of Bailey Bridge over Budhigang River at Jadanga Bajura along Sanfe - Martadi Road

Office: डिभिजन सडक कार्यालय, साँफेवगर, अछाम (178)

Fiscal Year: 077-78

100.00%

Contract Date: 27-Nov-20

Start Date: 28-Jan-21

Completion Date: 28-Jan-2021 (EOT Not Done)

Project Description

No description available.