Contract Agreement Amount
Rs. 22,25,242
Physical Progress
0.00%
Financial Progress
94.74%
Remaining Payment
Rs. 5
Black top works along BalmikiChakrapath, Nawalpur contract no. 56
Office: सडक डिभिजन, वुटवल (28)
Fiscal Year: 076-77
Contract Date: 20-Mar-20
Start Date: 20-Mar-20
Completion Date: 29-Jun-2020 (EOT Not Done)
Project Description
No description available.