Contract Agreement Amount

Rs. 84,38,734

Physical Progress

13.00%

Financial Progress

94.67%

Remaining Payment

Rs. 5

Construction of Slab Culvert, Gabion Structure and Gravelling Works in Pali to Balebang (Ch:53+000 to 58+000), Furbang(Ch:65+260),Gacche to Chutrabesi(Ch:70+000 to 72+000) & Rubdi (Ch:73+400) Section of Sandhikharka of Saljhandi Sandhikharka Dhorpatan Road(NH52)

Office: सालझण्डी सन्धिखर्क ढोरपाटन सडक योजना, अर्घाखांची (92)

Fiscal Year: 076-77

13.00%

Contract Date: 2-Jun-20

Start Date: 2-Jun-20

Completion Date: 04-Mar-2021 (EOT Done)

Project Description

No description available.