Contract Agreement Amount

Rs. 1,08,45,070

Physical Progress

100.00%

Financial Progress

94.49%

Remaining Payment

Rs. 5

Road upgrading works along Srijana Chowk (ARM) - DRO-Katunje VDC

Office: सडक डिभिजन, कञ्चनपुर (34)

Fiscal Year: 079-80

100.00%

Contract Date: 3-May-23

Start Date: 3-May-23

Completion Date: 05-Jul-2023 (EOT Not Done)

Project Description

No description available.