Contract Agreement Amount
Rs. 8,56,036
Physical Progress
0.00%
Financial Progress
94.44%
Remaining Payment
Rs. 5
Bio Engineering works at Gwarko Lakuri Bhanjyang Road Lalitpur.
Office: डिभिजन सडक कार्यालय, ललितपुर (23)
Fiscal Year: 078-79
Contract Date: 17-Jun-22
Start Date: 17-Jun-22
Completion Date: 15-Aug-2022 (EOT Not Done)