Contract Agreement Amount
Rs. 1,06,40,404
Physical Progress
93.00%
Financial Progress
94.32%
Remaining Payment
Rs. 5
Maintenance of Road by Construction of Roadway Structures, Humepipe Culverts and Earthworks in Bobang (Mongla), Baglung (CH 184+000) to Dhorpatan, Baglung (CH 197+000) section along Saljhandi-Sandikharka-Dhorpatan Road
Office: सालझण्डी सन्धिखर्क ढोरपाटन सडक योजना, अर्घाखांची (92)
Fiscal Year: 077-78
Contract Date: 3-May-21
Start Date: 3-May-21
Completion Date: 14-Sep-2022 (EOT Done)