Contract Agreement Amount
Rs. 13,75,90,770
Physical Progress
0.00%
Financial Progress
94.18%
Remaining Payment
Rs. 5
Upgrading of road of Ganeshchowk-Chyangthapu Sector
Office: Puspalal (Midhill) Road Project, Panchthar (273)
Fiscal Year: 070-71
Contract Date: 23-May-14
Start Date: 23-May-14
Completion Date: 25-Feb-2020 (EOT Done)
Project Description
No description available.