Contract Agreement Amount

Rs. 13,75,90,770

Physical Progress

0.00%

Financial Progress

94.18%

Remaining Payment

Rs. 5

Upgrading of road of Ganeshchowk-Chyangthapu Sector

Office: Puspalal (Midhill) Road Project, Panchthar (273)

Fiscal Year: 070-71

0.00%

Contract Date: 23-May-14

Start Date: 23-May-14

Completion Date: 25-Feb-2020 (EOT Done)

Project Description

No description available.