Contract Agreement Amount

Rs. 2,17,65,086

Physical Progress

100.00%

Financial Progress

94.13%

Remaining Payment

Rs. 5

Construction of RCC Bridge over Geuriya Khola at Lakhanpur-6 and Bishnukattha, Jhapa

Office: डिभिजन सडक कार्यालय, झापा (13)

Fiscal Year: 072-73

100.00%

Contract Date: 14-Jun-16

Start Date: 14-Jun-16

Completion Date: 01-Feb-2019 (EOT Done)

Project Description

No description available.