Contract Agreement Amount
Rs. 1,31,86,805
Physical Progress
100.00%
Financial Progress
94.09%
Remaining Payment
Rs. 5
Road Upgrading Works along Changuna pa 3 Gelalgaun Jyotilingesor road (Woda no 3 Office section)
Office: सडक डिभिजन, भक्तपुर (24)
Fiscal Year: 076-77
Contract Date: 14-Jun-20
Start Date: 14-Jun-20
Completion Date: 02-Feb-2021 (EOT Not Done)
Project Description
No description available.