Contract Agreement Amount

Rs. 18,56,05,195

Physical Progress

0.00%

Financial Progress

93.85%

Remaining Payment

Rs. 6

Construction of Pre stress motorable concrete bridge over Paundikhola between Sundarbajar Lamjung and Rupakot VDC in Tanahaun District

Office: सडक डिभिजन, तनहुं (25)

Fiscal Year: 073-74

0.00%

Contract Date: 2-Jul-17

Start Date: 2-Jul-17

Completion Date: 16-Aug-2020 (EOT Done)

Project Description

No description available.