Contract Agreement Amount
Rs. 75,16,490
Physical Progress
95.00%
Financial Progress
93.85%
Remaining Payment
Rs. 6
Structure & Blacktop Works on Phuljor Ishwarpur Babargunj Mohanpur Sadak, Sarlahi.
Office: डिभिजन सडक कार्यालय, चन्द्रनिगाहापुर, गौर (176)
Fiscal Year: 077-78
Contract Date: 1-Jun-21
Start Date: 1-Jun-21
Completion Date: 18-Feb-2023 (EOT Done)
Project Description
No description available.