Contract Agreement Amount
Rs. 98,65,074
Physical Progress
99.00%
Financial Progress
93.75%
Remaining Payment
Rs. 6
Roadway Upgrading Works along Campus Chowk -Pragatinagar Chowk - Salghari - Chuwadi Road, Nawalpur (Package 2)
Office: डिभिजन सडक कार्यालय, चितवन (20)
Fiscal Year: 078-79
Contract Date: 28-Apr-22
Start Date: 3-May-22
Completion Date: 13-Jan-2023 (EOT Done)