Contract Agreement Amount
Rs. 94,76,60,343
Physical Progress
94.20%
Financial Progress
93.73%
Remaining Payment
Rs. 6
Upgrading of Janakpur Basbitti Balba Hardi Pokhari Bhinda Sangrampur Road, Dhanusha/Mahottari.
Office: हुलाकी राजमार्ग आयोजना, योजना कार्यालय, जनकपुर, धनुषा (213)
Fiscal Year: 074-75
Contract Date: 26-Dec-17
Start Date: 24-Jan-18
Completion Date: 17-Jan-2024 (EOT Done)
Project Description
No description available.