Contract Agreement Amount
Rs. 35,89,32,300
Physical Progress
100.00%
Financial Progress
93.70%
Remaining Payment
Rs. 6
2. भादा खोला पुल, नेपालगंज-गुलरिया सडक
Office: पुल योजना, पश्चिम क्षेत्र सेक्टर नं. ३, वांके (190)
Fiscal Year: 073-74
Contract Date: 8-Dec-17
Start Date: 8-Dec-17
Completion Date: 12-May-2024 (EOT Done)
Project Description
No description available.