Contract Agreement Amount

Rs. 95,91,411

Physical Progress

97.00%

Financial Progress

93.53%

Remaining Payment

Rs. 6

Periodic Maintenence of kupondle ( Himalayan Hotel ) Jwagal Chakupat Road

Office: डिभिजन सडक कार्यालय, ललितपुर (23)

Fiscal Year: 078-79

97.00%

Contract Date: 8-Apr-22

Start Date: 17-Apr-22

Completion Date: 14-Oct-2022 (EOT Not Done)

Project Description

No description available.