Contract Agreement Amount
Rs. 61,05,025
Physical Progress
100.00%
Financial Progress
93.51%
Remaining Payment
Rs. 6
Road Upgrading Works on Kalesti -Gajude -Pokharichhap Hudhai Chandrawoti Sadak, Tanahun
Office: सडक डिभिजन, तनहुं (25)
Fiscal Year: 078-79
Contract Date: 27-Apr-22
Start Date: 27-Apr-22
Completion Date: 09-Jul-2022 (EOT Not Done)