Contract Agreement Amount
Rs. 2,23,46,417
Physical Progress
0.00%
Financial Progress
0.00%
Remaining Payment
Rs. 100
Maintenance of Flood Collapsed Bhapsi Khola Bridge along Mahendra Highway at ch 268+270
Office: Unknown (1)
Fiscal Year: 078-79
Contract Date: 28-Oct-23
Start Date: 28-Oct-23
Completion Date: 13-Jun-2022 (EOT Not Done)
Project Description
No description available.