Contract Agreement Amount
Rs. 46,53,500
Physical Progress
98.00%
Financial Progress
93.35%
Remaining Payment
Rs. 6
Road Improvement and construction of Cross Drainage Structures at Motena-Jimradi Sadak Sanfebagar Na Pa 8 Achham
Office: डिभिजन सडक कार्यालय, साँफेवगर, अछाम (178)
Fiscal Year: 076-77
Contract Date: 29-Dec-19
Start Date: 29-Dec-19
Completion Date: 12-May-2020 (EOT Not Done)
Project Description
No description available.