Contract Agreement Amount
Rs. 5,03,61,873
Physical Progress
92.00%
Financial Progress
93.31%
Remaining Payment
Rs. 6
चिरेगाड खोला पुल (बागर - मिरौली - बुलबुले जोडने सडक दाङ)
Office: सडक डिभिजन, दाङ्ग (31)
Fiscal Year: 076-77
Contract Date: 19-Oct-20
Start Date: 19-Oct-20
Completion Date: 15-Sep-2022 (EOT Not Done)