Contract Agreement Amount

Rs. 1,54,05,471

Physical Progress

94.00%

Financial Progress

93.13%

Remaining Payment

Rs. 6

Periodic Maintenance Works (Premix Overlay Works) along Damak Chakrapath (Buspark-Beldangi-Tarabari (MRM)-Setumari Section, Jhapa

Office: मध्यमाञ्चल क्षेत्रिय सडक निर्देशनालय, काठमाण्डौ (8)

Fiscal Year: 079-80

94.00%

Contract Date: 24-Nov-22

Start Date: 24-Nov-22

Completion Date: 05-Jul-2023 (EOT Not Done)