Contract Agreement Amount
Rs. 6,29,15,557
Physical Progress
80.00%
Financial Progress
92.94%
Remaining Payment
Rs. 7
Construction of RCC Bridge over Aduwa khola at MRM Birtamod jhapa
Office: डिभिजन सडक कार्यालय, झापा (13)
Fiscal Year: 073-74
Contract Date: 13-Jul-17
Start Date: 13-Jul-17
Completion Date: 13-Jan-2020 (EOT Done)