Contract Agreement Amount

Rs. 51,81,202

Physical Progress

0.00%

Financial Progress

92.93%

Remaining Payment

Rs. 7

Hariwon Na.Pa.-9 hudai Purba Paschim Rajmarg dekhi uttar Bishnupur hudai Purano Bajar Atrauli Pakar Gachhi hudai Ganesh Chowk Tibre Sadak, Sarlahi

Office: डिभिजन सडक कार्यालय, चन्द्रनिगाहापुर, गौर (176)

Fiscal Year: 076-77

0.00%

Contract Date: 11-Dec-19

Start Date: 11-Dec-19

Completion Date: 29-Jun-2020 (EOT Not Done)