Contract Agreement Amount

Rs. 2,33,55,624

Physical Progress

93.00%

Financial Progress

92.73%

Remaining Payment

Rs. 7

Construction of Pavement & Structural Works, Kailali (Ch.44+400 to 45+850)

Office: Unknown (1)

Fiscal Year: 080-81

93.00%

Contract Date: 8-Jan-24

Start Date: 8-Jan-24

Completion Date: 04-Jul-2024 (EOT Not Done)

Project Description

No description available.