Contract Agreement Amount

Rs. 21,39,54,290

Physical Progress

93.36%

Financial Progress

92.70%

Remaining Payment

Rs. 7

Construction of Sitalpur-Malangwa-Kharaiyatol Road, Sarlahi Package II (Ch 15+000 to 30+000)

Office: गाईघाट दिक्तेल सडक योजना, उदयपुर (63)

Fiscal Year: 072-73

93.36%

Contract Date: 17-Jul-16

Start Date: 17-Jul-16

Completion Date: 15-May-2023 (EOT Done)

Project Description

No description available.