Contract Agreement Amount

Rs. 9,27,297

Physical Progress

0.00%

Financial Progress

92.62%

Remaining Payment

Rs. 7

Installation of Bailey Bridge Over Sandhi Khola Araniko Highway

Office: डिभिजन सडक कार्यालय, दोलखा (18)

Fiscal Year: 075-76

0.00%

Contract Date: 3-Jul-19

Start Date: 3-Jul-19

Completion Date: 10-Jul-2019 (EOT Not Done)

Project Description

No description available.