Contract Agreement Amount

Rs. 41,17,670

Physical Progress

52.00%

Financial Progress

91.93%

Remaining Payment

Rs. 8

Roadway Excavation with Retaining Structures, Pipe Culverts, and Graveling works at Panthadihi Katahare Harmi Sahiltar Sadak, Gorkha.

Office: योजना तथा अनुगमन महाशाखा (भूवातावरण तथा सामाजिक शाखा) (4)

Fiscal Year: 079-80

52.00%

Contract Date: 12-Jan-23

Start Date: 12-Jan-23

Completion Date: 10-Jul-2023 (EOT Not Done)

Project Description

No description available.