Contract Agreement Amount

Rs. 2,37,01,152

Physical Progress

91.00%

Financial Progress

91.67%

Remaining Payment

Rs. 8

Construction of RCC Box Culvert (3 cells*6*5) at Simari Khola, Dokebazar-Belauri-Beldadi-Daije Road, Kanchanpur (8+740)

Office: मध्यमाञ्चल क्षेत्रिय सडक निर्देशनालय, काठमाण्डौ (8)

Fiscal Year: 078-79

91.00%

Contract Date: 3-Mar-22

Start Date: 3-Mar-22

Completion Date: 15-Feb-2023 (EOT Not Done)

Project Description

No description available.