Contract Agreement Amount
Rs. 1,85,76,941
Physical Progress
0.00%
Financial Progress
91.63%
Remaining Payment
Rs. 8
Maryadpur Sitalpur Mewa Sadak, Rautahat
Office: डिभिजन सडक कार्यालय, चन्द्रनिगाहापुर, गौर (176)
Fiscal Year: 076-77
Contract Date: 31-Jan-20
Start Date: 31-Jan-20
Completion Date: 26-Feb-2021 (EOT Done)
Project Description
No description available.