Contract Agreement Amount
Rs. 29,66,735
Physical Progress
100.00%
Financial Progress
91.60%
Remaining Payment
Rs. 8
Road Improvement Works along Bagmati Na.Pa.11 chure bhitte chauri dekhi Mudekhola Sadak Nirman, sarlahi
Office: डिभिजन सडक कार्यालय, चन्द्रनिगाहापुर, गौर (176)
Fiscal Year: 078-79
Contract Date: 9-Feb-22
Start Date: 9-Feb-22
Completion Date: 12-Jan-2023 (EOT Done)