Contract Agreement Amount

Rs. 81,62,72,787

Physical Progress

92.29%

Financial Progress

91.46%

Remaining Payment

Rs. 8

Construction of Blacktop Road Patibhanjyang Chahare Section in Nuwakot

Office: Puspalal (Midhill) Road Project, Gorkha (275)

Fiscal Year: 074-75

92.29%

Contract Date: 18-Sep-17

Start Date: 18-Sep-17

Completion Date: 08-Feb-2024 (EOT Done)

Project Description

No description available.