Contract Agreement Amount

Rs. 3,27,04,306

Physical Progress

97.00%

Financial Progress

91.43%

Remaining Payment

Rs. 8

Construction Of RCC Bridge Over Sikri Khola, Dolakha

Office: डिभिजन सडक कार्यालय, दोलखा (18)

Fiscal Year: 073-74

97.00%

Contract Date: 13-Oct-17

Start Date: 13-Oct-17

Completion Date: 14-Jan-2020 (EOT Done)