Contract Agreement Amount
Rs. 3,50,95,335
Physical Progress
92.00%
Financial Progress
91.40%
Remaining Payment
Rs. 8
Rehabilitation & Improvement of Existing Curve along Surkhet Dailekh Road (Chainage 5+000 - 25+000), Surkhet & Dailekh District
Office: सुदुरपच्चिमाञ्चल क्षेत्रिय सडक निर्देशनालय, डोटी (11)
Fiscal Year: 079-80
Contract Date: 17-Jan-23
Start Date: 17-Jan-23
Completion Date: 05-Jul-2023 (EOT Not Done)
Project Description
No description available.