Contract Agreement Amount
Rs. 2,23,98,573
Physical Progress
0.00%
Financial Progress
91.29%
Remaining Payment
Rs. 8
Construction of RCC Bridge Khahare Khola in Nuwakot
Office: Puspalal (Midhill) Road Project, Gorkha (275)
Fiscal Year: 073-74
Contract Date: 10-Jul-17
Start Date: 10-Jul-17
Completion Date: 10-Jul-2019 (EOT Not Done)
Project Description
No description available.