Contract Agreement Amount
Rs. 57,21,351
Physical Progress
98.00%
Financial Progress
91.09%
Remaining Payment
Rs. 8
Upgrading works of Barhabise 5jambu kaseri Road
Office: डिभिजन सडक कार्यालय, दोलखा (18)
Fiscal Year: 076-77
Contract Date: 19-Dec-19
Start Date: 19-Dec-19
Completion Date: 12-Apr-2020 (EOT Not Done)
Project Description
No description available.