Contract Agreement Amount
Rs. 35,72,449
Physical Progress
46.00%
Financial Progress
90.98%
Remaining Payment
Rs. 9
Construction of Black Topped Road and Cross Drainage Works at Garamuni Goldhap Bhutani Shibir Puhatubari Charali Road, Jhapa
Office: डिभिजन सडक कार्यालय, झापा (13)
Fiscal Year: 076-77
Contract Date: 8-Nov-19
Start Date: 8-Nov-19
Completion Date: 13-May-2020 (EOT Not Done)