Contract Agreement Amount
Rs. 42,52,24,530
Physical Progress
87.74%
Financial Progress
90.86%
Remaining Payment
Rs. 9
MIDHLDNG3371384/074/075
Office: Puspalal (Midhill) Road Project, Dailekh (277)
Fiscal Year: 074-75
Contract Date: 20-Jul-18
Start Date: 20-Jul-18
Completion Date: 16-Oct-2024 (EOT Done)
Project Description
No description available.