Contract Agreement Amount

Rs. 1,15,68,626

Physical Progress

0.00%

Financial Progress

90.78%

Remaining Payment

Rs. 9

Road Improvement works on Gangate Labdhu Samundratar Golphubhanjyang Road, Nuwakot (Package 3)

Office: डिभिजन सडक कार्यालय, नुवाकोट (21)

Fiscal Year: 076-77

0.00%

Contract Date: 27-May-20

Start Date: 27-May-20

Completion Date: 20-Dec-2020 (EOT Done)

Project Description

No description available.