Contract Agreement Amount

Rs. 2,44,09,092

Physical Progress

100.00%

Financial Progress

90.24%

Remaining Payment

Rs. 9

Construction of Dobal cell Ree box culvert (5x5) at Dora khola bara

Office: हुलाकी राजमार्ग आयोजना, योजना कार्यालय, वीरगंज, पर्सा (168)

Fiscal Year: 078-79

100.00%

Contract Date: 28-Feb-22

Start Date: 10-Mar-22

Completion Date: 01-Nov-2022 (EOT Not Done)