Contract Agreement Amount
Rs. 2,44,09,092
Physical Progress
100.00%
Financial Progress
90.24%
Remaining Payment
Rs. 9
Construction of Dobal cell Ree box culvert (5x5) at Dora khola bara
Office: हुलाकी राजमार्ग आयोजना, योजना कार्यालय, वीरगंज, पर्सा (168)
Fiscal Year: 078-79
Contract Date: 28-Feb-22
Start Date: 10-Mar-22
Completion Date: 01-Nov-2022 (EOT Not Done)
Project Description
No description available.