Contract Agreement Amount
Rs. 3,10,43,581
Physical Progress
55.00%
Financial Progress
90.22%
Remaining Payment
Rs. 9
Construction of Gundre Khola Bridge (RCC1X15m), Nuwakot
Office: गल्छी त्रिशुली मैलुङ्ग स्याफ्रुवेशी रसुवागढी सडक योजना, विदुर नुवाकोट (83)
Fiscal Year: 076-77
Contract Date: 11-Nov-20
Start Date: 11-Nov-20
Completion Date: 08-Apr-2022 (EOT Not Done)
Project Description
No description available.