Contract Agreement Amount

Rs. 9,49,69,079

Physical Progress

100.00%

Financial Progress

90.03%

Remaining Payment

Rs. 9

Construction & Improvement of Garuda Katahariya Kalaiya Birgunj Road, Rautahat

Office: डिभिजन सडक कार्यालय, चन्द्रनिगाहापुर, गौर (176)

Fiscal Year: 077-78

100.00%

Contract Date: 30-May-21

Start Date: 30-May-21

Completion Date: 31-Mar-2023 (EOT Done)

Project Description

No description available.