Contract Agreement Amount

Rs. 4,07,68,477

Physical Progress

95.66%

Financial Progress

5.00%

Remaining Payment

Rs. 95

Roadway improvement work n chinchu Jajarkot Road (CH 0+000 to 6+000 & 30+000 to 44+000 )

Office: सडक डिभिजन, सुर्खेत (33)

Fiscal Year: 077-78

95.66%

Contract Date: 15-Apr-21

Start Date: 22-Apr-21

Completion Date: 09-Jul-2021 (EOT Not Done)

Project Description

No description available.