Contract Agreement Amount

Rs. 8,09,46,787

Physical Progress

95.00%

Financial Progress

89.95%

Remaining Payment

Rs. 10

मुक्तिनाथ नि.से.

Office: उत्तर दक्षिण (कालिगण्डकी करिडोर) लोकमार्ग योजना, पाल्पा (171)

Fiscal Year: 072-73

95.00%

Contract Date: 14-Jul-16

Start Date: 17-Jul-17

Completion Date: 28-Dec-2020 (EOT Done)