Contract Agreement Amount

Rs. 11,57,86,785

Physical Progress

2.40%

Financial Progress

89.44%

Remaining Payment

Rs. 10

Seti Nadi(Tamail )Bridge Bajhang

Office: सेती राजमार्ग (उत्तर खण्ड​) चैनपुर ताक्लाकोट सडक योजना, बझाङ्ग (222)

Fiscal Year: 072-73

2.40%

Contract Date: 13-Jul-16

Start Date: 14-Jan-19

Completion Date: 09-Jul-2022 (EOT Done)

Project Description

No description available.