Contract Agreement Amount

Rs. 11,44,38,614

Physical Progress

89.41%

Financial Progress

89.41%

Remaining Payment

Rs. 10

Periodic Maintenance of Duhabi (KRM)-Inarwa (Km 0.000 to km 8.000 of Fo54_01), Bardanga- Urlabari (MRM) (Km 0.000 to Km 19.38 of Fo60-01), Mawa Harichamod ( Km 54.750 to km 63.450 of NH01-006), Biratnagar Division DOR

Office: डिभिजन सडक कार्यालय, मोरङ (14)

Fiscal Year: 078-79

89.41%

Contract Date: 11-Mar-22

Start Date: 11-Mar-22

Completion Date: 25-Apr-2024 (EOT Done)

Project Description