Contract Agreement Amount

Rs. 1,18,14,886

Physical Progress

90.00%

Financial Progress

89.37%

Remaining Payment

Rs. 10

Rehab/ReConstruction Works on Mechi-Highway NH02 Jhapa

Office: योजना तथा अनुगमन महाशाखा (HMIS तथा ICT शाखा) (6)

Fiscal Year: 078-79

90.00%

Contract Date: 18-Oct-21

Start Date: 18-Oct-21

Completion Date: 15-Mar-2022 (EOT Not Done)

Project Description

No description available.