Contract Agreement Amount
Rs. 70,80,62,902
Physical Progress
100.00%
Financial Progress
89.22%
Remaining Payment
Rs. 10
upgrading of jaleshor hardi road mahottari ch 0+000-28+000-073.74.UR017
Office: हुलाकी राजमार्ग निर्देशनालय, काठमाण्डौ (230)
Fiscal Year: 073-74
Contract Date: 12-Jun-17
Start Date: 28-Jun-17
Completion Date: 11-Dec-2020 (EOT Done)