Contract Agreement Amount
Rs. 75,61,784
Physical Progress
100.00%
Financial Progress
89.03%
Remaining Payment
Rs. 10
Recurrent Maintenance works along MRM Butwal- Kothi Section (Murgiya to Saljhandi Bajar, CH 14+000 to 22+000) & SRM Chidiyakhola-Siddhababa Road Section
Office: सडक डिभिजन, वुटवल (28)
Fiscal Year: 078-79
Contract Date: 4-May-22
Start Date: 4-May-22
Completion Date: 07-Nov-2022 (EOT Not Done)
Project Description
No description available.